Engineering progress of Haikou Integrated Free Trade Zone
2015-08-13 18:04
Engineering progress of Haikou Integrated Free Trade Zone:
Factory A: Interior equipment debugging and staff training are underway. It is expected to commence trial production in end-June 2016.
Multiple-use Building: NGTC Laboratory and customs office have been renovated, and the opening ceremony has been held. It is expected to be brought into service in end-June 2016.
Exhibition Center, Factory B / C, and Warehouse A / B / C / D: They are expected to be brought into service entirely in end-June 2016. The field engineering has been completed, and the acceptance of the project is underway.